Grid Metals Corp (TSXV:GRDM) (OTCQB:MSMGF) reported results from an additional 12 holes at its Donner Lake Lithium Property, located 150 km northeast of Winnipeg Manitoba. The drilling is part of the maiden 43-101 compliant resource delineation program at Donner Lake. The current phase of drilling at the Main Dyke has now been completed.
| Drill hole | Li2O | Interval (m) | From (m) | |
| GDL-22-26 | 1.7% | 1.9 | 190.0 | |
| and | 1.2% | 0.8 | 287.2 | |
| and | 2.0% | 5.9 | 291.5 | |
| and | 1.6% | 2.7 | 302.8 | |
| GDL22-27 to GDL22-30 previously reported | ||||
| GDL22-31 | 1.4% | 5.3 | 187.3 | |
| GDL22-32 | 1.8% | 6.1 | 230.0 | |
| GDL22-33 | 2.1% | 1.7 | 110.3 | |
| and | 1.5% | 5.9 | 252.1 | |
| GDL22-34 | 1.5% | 3.4 | 50.8 | |
| GDL22-35 | 1.6% | 3.8 | 175.0 | |
| GDL22-36 | 1.8% | 3.5 | 60.8 | |
| GDL22-37 | 1.8% | 7.5 | 213.5 | |
| including | 2.1% | 4.0 | 217.0 | |
| GDL22-38 | 1.7% | 3.6 | 139.4 | |
| GDL22-39 | Assays pending | |||
| GDL22-40 | 1.7% | 3.8 | 151.5 | |
| GDL22-41 | 1.8% | 5.3 | 178.3 | |
| GDL22-42 | 1.8% | 3.3 | 212.4 | |
| and | 1.6% | 4.4 | 295.3 | |
Above: Table of length-weighted average LiO2 concentrations for drill holes GDL22-26 and GDL22-31 to GDL22-42 drilled on the Main Dyke including results from GDL22-26 which had not been previously released. Interval lengths are apparent widths with true widths generally estimated to represent between 50% and 80% of the reported interval lengths depending on the hole orientation UTM coordinates, azimuth and dip of above holes are tabulated later in this release.
The Main Dyke resource delineation drilling has confirmed a minimum vertical depth of approximately 350m over a minimum strike length of approximately 800 metres. The Company is pleased to note that the deepest holes completed to date at the Main Dyke continue to show excellent spodumene content and consistent widths.
Resource drilling will now shift to the Northwest Dykes where a ~ 600m strike length has been outlined for delineation.
The Company is pleased to note that it has received initial results from a drone mag survey over the core area at Donner Lake. The survey results will be integrated with lithogeochemical data generated by the 2022 field program to assess and prioritize new exploration targets for the property.
Donner Lake Lithium is a 75%/25% joint venture project between Lithium Royalty Corp and Grid Metals Corp. with Grid Metals as the project operator. Resource drilling at two known LCT spodumene bearing dykes is expected to be competed by end of March 2023 to be followed by an initial NI 43-101 resource estimate. An Advanced Exploration Permit application is being prepared which would enable a bulk sample which planned to be completed at the nearby Tanco Mine – Canada’s only hardrock lithium producer. Grid has a MOU in place with Tanco for possible toll milling at the Tanco Mine.
Ecora (LSE:ECOR)(TSX:ECOR)(OTCQX:ECRAF) notes the announcement on 4 September by Vale Base Metals that it has…
Highlights • A$14.1M Entitlement Offer received strong demand from Australian, Canadian and international shareholders •…
Ecora Resources PLC (LSE:ECOR)(TSX:ECOR)(OTCQX:ECRAF) announced half year results for the six months ended 30 June…
First Nordic Metals Corp. (TSXV: FNM) (FNSE: FNMC SDB) (OTCQB: FNMCF) (FRA: HEG0) announced the…
Ecora (LSE/TSX: ECOR, OTCQX: ECRAF) announced that it has agreed to sell a wholly-owned subsidiary,…
Power Metallic Mines Inc. (TSXV: PNPN) (OTCBB: PNPNF) (Frankfurt: IVV) announced the appointment of Seamus…